Part II Renovation Process 2/3

Updated: 6 days ago

On this week's presentation of a renovation.

items needed for installation, Measurements for carpentry and Plumbing works.



1. Electrical

1st Phase

The electrical points, Proposed idea of the placement of lighting, Socket points, ceiling fan & LED cove lights installation.


2nd Phase

Works begin, removing loose/Unused wires for safety reasons.

We begin to extend points in the house and proceed with follow-ups. Install all lighting in the home takes about 1-3 days to proceed with running the cabling and installing the lights.


3rd Phase

Touch up electrical issues finalising the major/minor issues of the lighting.

If need be changes to confirm a better option.


Duration: 1-2 days




2. Carpentry

Carpentry is the part where most options turn to Ikea with the producing cheaper alternative.

However Designed & Fabricated Carpentry gives the importance of interior design fitting your style and design into your home. Tv console, Kitchen Cabinets & etc etc. Designed & Fabricated Carpentry precise measurements needed to be taken before the start of the fabrication.


Examples of some of our carpentry drafting works


Measurements: 1 day

Design& Fabricate: 2-4 weeks

Installation: 1 weeks


Duration: Depends on the amount of carpentry needed to build.




3. Plumbing

The owner has to purchase all toilet accessories & designed vanity. How fast can it be delivered? After purchasing it takes about 1 week. Shout out to lights & bathroom solutions!


The plumber then has to fix up all accessories and if needed, change water pipes and install toilet & kitchen sinks.


Duration: 1-3 days



Entire process takes about a month to finish your DREAM HOME